POTWASHER CE-UWL Installation Checklist

Use this pre-installation checklist to confirm power, water, drainage, exhaust, floor and clearance before the CE-UWL ships. Download the PDF or work through the list below.

Download Checklist (PDF)

The printable PDF (potwasher-installation-checklist-v1.pdf) is being finalized. If it is not yet available, email [email protected], or use the checklist below.

Power

  • ☐ Supply confirmed: 380V/50Hz/3PH (or 220V/1PH variant ordered)
  • ☐ Capacity for 27.4 kW total load, 10 mm² cable, correctly-rated breaker

Water & drainage

  • ¾" inlet at 0.2–0.5 MPa available
  • 1½" drain with trap nearby
  • ☐ Water hardness < 5 °dH, or softener planned

Exhaust & floor

  • φ175 mm exhaust path to overhead hood
  • ☐ Level concrete floor with drain nearby

Space & access

  • 1030 × 895 × 1825 mm footprint with front door clearance and rear service access
  • ☐ Delivery route confirmed for the crated machine

Full installation guide →