CE-UWL Installation Guide for Buyers & Contractors

The CE-UWL needs a 1030 × 895 mm floor area with clearance, 380V/50Hz/3-phase power at 27.4 kW, a ¾" water inlet and 1½" drain, and a φ175 mm exhaust path. Confirm these before the machine ships to avoid installation delays.

Site requirements summary

Plan for floor space and clearance, ceiling height for steam, an exhaust path, three-phase power, a water inlet and outlet, and floor drainage near the machine.

Power

  • Standard: 380V / 50Hz / 3PH; option: 220V / 50Hz / 1PH
  • Total connected load: 27.4 kW
  • Supply cable: 10 mm² with an appropriately-rated breaker

Water

  • Inlet: ¾" at 0.2–0.5 MPa
  • Outlet/drain: 1½" with a trap nearby
  • Recommended hardness: < 5 °dH, otherwise fit a softener

Exhaust & floor

  • Exhaust: φ175 mm pipe to an overhead hood
  • Floor: level concrete with a drain nearby

Footprint & clearance

External dimensions are 1030 × 895 × 1825 mm. Allow front clearance for the fold-down door and loading, plus rear access for plumbing and exhaust. Verify the crated machine can route through doorways and corridors to the install point.

Commissioning

  1. Factory pre-test before shipment.
  2. On-site setup and connection by local trades.
  3. Calibration and dry-run, guided remotely over WhatsApp video.
  4. Operator training.

Installation checklist (PDF)